Capital Campaign Prayer
- 1930's - Parish Hall built
- 1996 - Vestry retreat begins the process
- 1997 - Vestry begins to address need for more Class Room Space
- 1998 - Vestry discussed Pro's and Con's of tearing down existing Parish house and rebuilding it.
- 1999 - Vestry voted to start a new project and hired the Johnson / Fox architecture firm
- 2000 - (August) - Letters to neighbors about project
- 2000 - Parish profile said "Behind the church is the Parish Hall, which, at present time is too small for our congregation. The Vestry has hired an architect to design a handicap-accessible two-level building to accommodate parish and community activities. The upper level will have a great room, closets for chairs and tables, a large kitchen, and rest rooms. The lower level will have seven or eight classrooms, storage areas, a nursery, rest rooms, utility room, and an elevator shaft. After the alterations, the Parish Hall, church, and the Mitcham House will all be connected and barrier-free."
- 2001 - March 26 - Joe Wnuck Update to Parish

- 2001 - March 30 - Historical Society to walk through Parish Hall
- 2001 - April 16 - Before the Historical Society for the first time
- 2001 - April 26 - Revised Drawings for Historical Society

- 2001 - May 13 - Approved additional costs for revisions

- 2001 - June 14 - Received revised plans

- 2001 - July 26 - Revised plans mailed to Historical Society

- 2001 - August 14 - Plans reviewed by Building Committee

- 2001 - September 9 - Plans presented to congregation

- 2002 - Annual Report

- 2002 - Approval from Historical Commission
- 2002 - January 15 - Before the Hackettstown Planning Board

- 2002 - February 19 - Reappear before Planning Board

- 2002 - March 19 - Another appearance before the Board

- 2002 - April 16 - One more time

- 2002 - May 22 - Another time before the Board

- 2002 - (May) Zoning Board Denied Improvements

- 2002 - May 22 -
Our variance
application was defeated

- 2002 - (October) Project Time Line reviewed

- 2002 - December 19th, Project Approved

- 2003 - (February) Ready to begin Building Project

- 2003 - (February) Building Committee Begins Work

- 2003 - (February) Mr. Joseph Wnuck dies (01/09/03)

- 2003 - (March) Building project update

- 2003 - (April) Building project update

- 2003 - (May) Building Project Parish Meeting Announced

- 2003 - May 18 - Parish Meeting

- 2003 - (June) Rector's letter from May 18th Parish Meeting

- 2003 - (June) Wardens report in Journal about May 18 Meeting

- 2003 - October 5 - Bethsaida Team Visit

- 2003 - (October) Accessibility at St. James

- 2003 - (October) Fundraising begins
- 2004 - (March) Building Project and Vestry Retreat

- 2004 - March 14 - Project Reintroduced at Parish Forums

- 2004 - (April) Building Project Forum

- 2004 - (May) Capital Campaign announced

- 2004 - (June) Wardens update
- 2004 - (October) Feasibility Study

- 2004 - (October) Feasibility Study to Vestry

- 2004 - (November) Wardens Update

- 2004 - November 13 - Bob the Builder Party

- 2004 - (December) Capital Campaign Planning

- 2005 - (January) Capital Campaign Executive Committee

- 2005 - (February) Capital Campaign Committee

- 2005 - (March) Capital Campaign behind the scenes

- 2005 - (April) First Capital Campaign Goals

- 2005 - (April) Open Door Campaign announced

- 2005 - (April) Capital Campaign Events

- 2005 - (April) High Tea at Heath Village

- 2005 - (May) Open Door Campaign


- 2005 - (June) Ice Cream Social


- 2006 - (February) Open Door Campaign Update


- 2006 - April 20 - Request For Proposal Bids Due

- 2006 - (October) Building Project Update

- 2006 - (October) Contract awarded to Rochelle Construction

- 2006 - (November) Building Project Update

- 2006 - January 21 - Moving Day

- 2007 - Virtual Tour - Prior to Demolition

- 2007 - April 19 - Fire Drill #1

- 2007 - April 23 - Fire Drill #2

- 2007 - April 27 - Demolition Day 1

- 2007 - April 28 - Demolition Day 2

- 2007 - April 29 - Parish Hall Down

- 2007 - April 30 - Demolition Done, Clean Up Begins

- 2007 - (May) Building Project Begins ... Again

- 2007 - May 2 - Clean Up

- 2007 - May 3 - All Cleaned Up

- 2007 - May 7 & 9 - Excavation Begins
- 2007 - May 9 - Project On Hold for Paperwork
A link to a Slide Show Calendar, so that you can watch the building of the new Parish Hall.